VIKTIGE MILEPΖLER:
24.08.2004 - Project directive started
03.09.2004 - Project directive ended
06.09.2004 - Preliminary study started
17.09.2004 - Preliminary study ended
20.09.2004 - Construction started
15.10.2004 - Construction ended
18.10.2004 - Implementation started
25.10.2004 - Implementation ended
25.10.2004 - Testing started
28.10.2004 - PRELEVERANSE AV FORSTUDIUM OG KRAVSPEK
29.10.2004 - Testing ended
01.11.2004 - Evaluation started
04.11.2004 - Evaluation ended
09.11.2004 - Presentation and demonstration started
17.11.2004 - Presentation and demonstration ended
18.11.2004 - PRESENTATION
VIKTIGE AKTIVITETER:
24.08.2004 - Oppstart med veiledere og kunder
26.08.2004 - Forelesning om prosjektplanlegging og prosjektdirektiv
27.08.2004 - Seminar i gruppedynamikk, "Seks tenkehatter"
31.08.2004 - Kurs i CVS m/eclipse
06.09.2004 - Seminar i gruppedynamikk, "Teambuilding"
07.09.2004 - Forelesning om forstudie og kravspek
09.09.2004 - Eksempler og use caser
28.09.2004 - Forelesning i programvarearkitektur (R9)
30.09.2004 - Eksempler, konstruksjon og testing (R9)
30.09.2004 - Konstruksjon og testing (F1)
28.10.2004 - Preleveranse forstudium og kravspek (IT110)
29.10.2004 - Kurs i presentasjonsteknikk (EL6)
08.11.2004 - Bestille tid for kopiering av sluttrapport og hent cd'er (IT122)
15.11.2004 - Kopiering av sluttrapport
18.11.2004 - Prosjektpresentasjon
|
|
©