Schedule
| Date |
Milestone |
PDF |
Updated |
| 08.05.06 |
Finish second draft of report outline |
Report outline |
08.05.06 |
| 10.05.06 |
Finish UbiCollab and OSGi background |
OSGi : UbiCollab |
10.05.06 |
| 14.05.06 |
Finish main parts of problem elaboration (ch.2) and OSGi analysis (ch.3) |
Chapter 2 : Chapter 3 |
29.05.06 |
| 19.05.06 |
Finish discussion on platform's bundles (Overview + Details) |
N/A |
N/A |
| 21.05.06 |
Finish main parts of UbiCollab discussion (Theory + implementation) (ch.4/5) |
Chapter 4 : Chapter 5 |
29.05.06 |
| 24.05.06 |
Finish discussion on platform demonstration |
N/A |
N/A |
| 29.05.06 |
Finish main parts of demonstration (ch.6) and introduction (ch.1) |
Chapter 6 : Chapter 1 |
29.05.06 |
| 31.05.06 |
Finish draft 1 of final report |
N/A |
N/A |
| 16.06.06 |
Deliver final report |
N/A |
N/A |